A 5x8 bathroom remodel may appear simple due to its compact size, but the timeline can vary depending on the scope, materials, and labor efficiency. Whether you're doing a full renovation or a minor facelift, understanding the realistic timeline for a 5x8 bathroom remodel is crucial for setting expectations and avoiding costly delays.
Understanding the Scope of a 5x8 Bathroom Remodel
Before diving into the timeline, it’s essential to define what kind of remodel you're undertaking. A cosmetic remodel new paint, vanity, fixtures takes far less time than a full gut renovation, which may involve demolishing walls, relocating plumbing, or replacing subflooring.
Typical Types of 5x8 Bathroom Remodels:
Cosmetic Remodel: Replacing fixtures, paint, lighting, and accessories.
Mid-Range Remodel: Updating bathtub/shower, toilet, flooring, tiles, vanity, and lighting.
High-End Remodel: Full layout change, luxury finishes, advanced electrical and plumbing upgrades.
How Long Does It Take to Remodel a 5x8 Bathroom?
A standard 5x8 bathroom remodel timeline ranges between 2 to 4 weeks for professionals, but DIY efforts may extend this to 5 to 9 weeks, depending on skill level, availability, and complexity.
Week-by-Week Remodeling Timeline
Week 1: Planning, Permits, and Demolition
Duration: 3-5 days
Key tasks:
Finalizing the design and material selections
Securing necessary permits from local authorities
Scheduling subcontractors (plumber, electrician, tile setter)
Demolishing old fixtures, tiles, vanity, and drywall if needed
Disposal of waste material
Tips:
Always shut off water and electricity before demolition.
Use this week to pre-order custom fixtures (tubs, tiles, vanities) to avoid future delays.
Week 2: Plumbing and Electrical Rough-In
Duration: 2-4 days
Key tasks:
Installing or moving plumbing lines for the sink, toilet, tub, or shower
Upgrading or rerouting electrical wiring to meet code
Adding new outlets, recessed lighting, or vent fan wiring
Inspection Tip: Depending on your jurisdiction, building inspectors may need to approve the rough-in work before proceeding.
Week 3: Drywall, Waterproofing, and Flooring
Duration: 4-6 days
Key tasks:
Hanging drywall and cement boards
Taping, mudding, and sanding the drywall
Waterproofing the shower/tub surround using RedGard or waterproof membranes
Installing flooring (tile, vinyl, or waterproof laminate)
Best Practice: Ensure all surfaces are level and dry before tile installation to prevent future cracking.
Week 4: Tile, Paint, and Fixture Installation
Duration: 5-7 days
Key tasks:
Setting wall tiles for shower or tub surround
Grouting and sealing tile
Painting walls and ceiling
Installing vanity, sink, toilet, and lighting fixtures
Connecting plumbing and testing for leaks
Caution: Allow sufficient time for tile adhesive and grout to cure before exposing to water.
Final Days: Touch-Ups and Inspection
Duration: 2-3 days
Key tasks:
Final cleanup and debris removal
Caulking around tub, toilet base, sink, and tile edges
Final inspection by local authorities (if needed)
Walkthrough with the contractor to fix any punch-list items
Factors That Can Extend the Remodel Timeline
1. Material Delays
Ordering custom cabinets, tiles, or fixtures can delay the schedule by several weeks. Always place orders early and confirm shipping timelines.
2. Permitting and Inspections
In some cities, building permits and inspections can add 1-2 weeks to the remodel process, especially if you are moving plumbing or electrical.
3. Contractor Scheduling Conflicts
Good contractors are often booked in advance. Plan ahead and secure professionals early to avoid waiting.
4. Scope Creep
Midway changes to layout or materials will push your remodel off-schedule. Stick to the approved plan to maintain your timeline.
DIY vs. Professional Remodel: Which Is Faster?
Professional Remodel: ~3 weeks with a dedicated crew and streamlined process
DIY Remodel: ~6-8 weeks due to limited time, tools, and experience
While DIY may save money, it often leads to extended timelines and can result in errors that cost more to fix later.
Average Cost vs. Time: What to Expect
Remodel Type | Average Cost (USD) | Estimated Time |
---|
Cosmetic Remodel | $3,000 – $6,000 | 1–2 weeks |
Mid-Range Remodel | $8,000 – $15,000 | 3–4 weeks |
High-End Remodel | $18,000 – $30,000+ | 4–6 weeks |
Pro Tips to Speed Up Your Bathroom Remodel
1. Pre-order everything. Fixtures, tiles, and custom cabinetry should arrive before demo begins.
2. Hire licensed professionals. Streamlines permitting and inspection.
3. Use premade vanities or shower kits. Reduces custom labor and time.
4. Stick to the plan. Midway changes can add weeks to your schedule.
5. Plan for the unexpected. Rotten subfloors, outdated plumbing, or wiring issues can delay your timeline.
Conclusion
While timelines vary, a well-organized remodel of a 5x8 bathroom usually takes between 3 to 4 weeks when managed by experienced professionals. DIY remodels can stretch longer, but with strategic planning, realistic goals, and a clear scope, your small bathroom can be transformed quickly and efficiently into a functional and beautiful space.