How Long Does A 5×8 Bathroom Remodel Take

May 26, 2025

Written by: Deane Biermeier / Facts Checked by; Ryan Cullenward / Products Tested by Licensed Interior Designers

  • Home
  • /
  • Blog
  • /
  • How Long Does A 5×8 Bathroom Remodel Take

A 5x8 bathroom remodel may appear simple due to its compact size, but the timeline can vary depending on the scope, materials, and labor efficiency. Whether you're doing a full renovation or a minor facelift, understanding the realistic timeline for a 5x8 bathroom remodel is crucial for setting expectations and avoiding costly delays.

Understanding the Scope of a 5x8 Bathroom Remodel

Before diving into the timeline, it’s essential to define what kind of remodel you're undertaking. A cosmetic remodel new paint, vanity, fixtures takes far less time than a full gut renovation, which may involve demolishing walls, relocating plumbing, or replacing subflooring.

Typical Types of 5x8 Bathroom Remodels:

Cosmetic Remodel: Replacing fixtures, paint, lighting, and accessories.

Mid-Range Remodel: Updating bathtub/shower, toilet, flooring, tiles, vanity, and lighting.

High-End Remodel: Full layout change, luxury finishes, advanced electrical and plumbing upgrades.

How Long Does It Take to Remodel a 5x8 Bathroom?

A standard 5x8 bathroom remodel timeline ranges between 2 to 4 weeks for professionals, but DIY efforts may extend this to 5 to 9 weeks, depending on skill level, availability, and complexity.

Week-by-Week Remodeling Timeline

Week 1: Planning, Permits, and Demolition

Duration: 3-5 days

Key tasks:

Finalizing the design and material selections

Securing necessary permits from local authorities

Scheduling subcontractors (plumber, electrician, tile setter)

Demolishing old fixtures, tiles, vanity, and drywall if needed

Disposal of waste material

Tips:

Always shut off water and electricity before demolition.

Use this week to pre-order custom fixtures (tubs, tiles, vanities) to avoid future delays.

Week 2: Plumbing and Electrical Rough-In

Duration: 2-4 days

Key tasks:

Installing or moving plumbing lines for the sink, toilet, tub, or shower

Upgrading or rerouting electrical wiring to meet code

Adding new outlets, recessed lighting, or vent fan wiring

Inspection Tip: Depending on your jurisdiction, building inspectors may need to approve the rough-in work before proceeding.

Week 3: Drywall, Waterproofing, and Flooring

Duration: 4-6 days

Key tasks:

Hanging drywall and cement boards

Taping, mudding, and sanding the drywall

Waterproofing the shower/tub surround using RedGard or waterproof membranes

Installing flooring (tile, vinyl, or waterproof laminate)

Best Practice: Ensure all surfaces are level and dry before tile installation to prevent future cracking.

Week 4: Tile, Paint, and Fixture Installation

Duration: 5-7 days

Key tasks:

Setting wall tiles for shower or tub surround

Grouting and sealing tile

Painting walls and ceiling

Installing vanity, sink, toilet, and lighting fixtures

Connecting plumbing and testing for leaks

Caution: Allow sufficient time for tile adhesive and grout to cure before exposing to water.

Final Days: Touch-Ups and Inspection

Duration: 2-3 days

Key tasks:

Final cleanup and debris removal

Caulking around tub, toilet base, sink, and tile edges

Final inspection by local authorities (if needed)

Walkthrough with the contractor to fix any punch-list items

Factors That Can Extend the Remodel Timeline

1. Material Delays

Ordering custom cabinets, tiles, or fixtures can delay the schedule by several weeks. Always place orders early and confirm shipping timelines.

2. Permitting and Inspections

In some cities, building permits and inspections can add 1-2 weeks to the remodel process, especially if you are moving plumbing or electrical.

3. Contractor Scheduling Conflicts

Good contractors are often booked in advance. Plan ahead and secure professionals early to avoid waiting.

4. Scope Creep

Midway changes to layout or materials will push your remodel off-schedule. Stick to the approved plan to maintain your timeline.

DIY vs. Professional Remodel: Which Is Faster?

Professional Remodel: ~3 weeks with a dedicated crew and streamlined process

DIY Remodel: ~6-8 weeks due to limited time, tools, and experience

While DIY may save money, it often leads to extended timelines and can result in errors that cost more to fix later.

Average Cost vs. Time: What to Expect

Remodel TypeAverage Cost (USD)Estimated Time
Cosmetic Remodel$3,000 – $6,0001–2 weeks
Mid-Range Remodel$8,000 – $15,0003–4 weeks
High-End Remodel$18,000 – $30,000+4–6 weeks

Pro Tips to Speed Up Your Bathroom Remodel

1. Pre-order everything. Fixtures, tiles, and custom cabinetry should arrive before demo begins.

2. Hire licensed professionals. Streamlines permitting and inspection.

3. Use premade vanities or shower kits. Reduces custom labor and time.

4. Stick to the plan. Midway changes can add weeks to your schedule.

5. Plan for the unexpected. Rotten subfloors, outdated plumbing, or wiring issues can delay your timeline.

Conclusion

While timelines vary, a well-organized remodel of a 5x8 bathroom usually takes between 3 to 4 weeks when managed by experienced professionals. DIY remodels can stretch longer, but with strategic planning, realistic goals, and a clear scope, your small bathroom can be transformed quickly and efficiently into a functional and beautiful space.

Disclosure: Sanitarysupply.org receives an affiliate commission on some, but not all, of the products we recommend—but only if you decide to click through to the retailer's site and make a purchase.


You may also like

How To Finance A Bathroom Remodel

A bathroom remodel is one of the most impactful investments homeowners can make. Not only does it enhance daily comfort and functionality, but it also increases property value. However, funding a renovation can be a daunting task. In this comprehensive guide, we’ll break down strategic and effective methods to finance a bathroom remodel, providing you

Read More

How To Start A Bathroom Remodel

A bathroom remodel is more than a cosmetic update it’s a strategic investment in your home’s value, functionality, and aesthetic appeal. Whether you’re planning a full gut renovation or a simple upgrade, starting with a clear, structured plan is essential. Our guide offers a comprehensive roadmap to ensure your bathroom remodel is executed efficiently, beautifully,

Read More

How Much Does It Cost To Remodel A Bathroom In California

Bathroom remodels in California are among the most sought-after home improvement projects due to their ability to boost property value, increase comfort, and modernize living spaces. Understanding how much it costs to remodel a bathroom in California is essential before starting your renovation journey. Costs can vary greatly depending on size, materials, labor, and location

Read More

How Much Is A Typical Bathroom Remodel

Remodeling a bathroom is one of the most impactful upgrades a homeowner can undertake, not only for enhancing comfort and functionality but also for significantly boosting property value. But when it comes to budgeting a bathroom remodel, many homeowners are left asking: How much does it actually cost?Below, we break down all aspects of a