How Long Does A Bathroom Remodel Take

May 19, 2025
how long does a bathroom remodel take

Written by: Deane Biermeier / Facts Checked by; Ryan Cullenward / Products Tested by Licensed Interior Designers

  • Home
  • /
  • Blog
  • /
  • How Long Does A Bathroom Remodel Take

When planning a bathroom renovation, one of the most pressing questions homeowners ask is: how long does a bathroom remodel take? The truth is, the timeline can vary greatly depending on the size of the bathroom, the scope of the work, the materials used, and whether you're hiring professionals or doing some tasks yourself.

In this detailed guide, we break down every stage of a bathroom remodel to give you a realistic and comprehensive timeline you can plan around.

Average Time for a Bathroom Remodel

On average, a standard bathroom remodel takes about 3 to 6 weeks once the actual construction begins. However, pre-construction planning and materials procurement can add 2 to 4 weeks more. For larger or luxury bathrooms, or those with extensive changes like relocating plumbing or upgrading electrical systems, the project can stretch to 8 to 10 weeks or longer.

Phase 1: Planning and Design (1–2 Weeks)

Before any demolition or construction starts, planning is essential. During this phase, we:

Evaluate the existing bathroom layout and structural constraints

Define the scope of the renovation

Choose materials, fixtures, and finishes

Finalize the bathroom design layout

Gather estimates and select the contractor (if not DIY)

If custom cabinetry, special order tiles, or luxury fixtures are involved, lead times can extend this phase. Proper planning helps avoid costly delays later.

Phase 2: Permits and Ordering Materials (1–3 Weeks)

Depending on your location and the scope of your remodel, you may need permits for plumbing, electrical, and structural changes. This process can take anywhere from a few days to a few weeks, depending on local government processing times.

At the same time, all materials and fixtures should be ordered, including:

Vanity and countertop

Shower or tub units

Toilets

Sinks and faucets

Flooring

Lighting and mirrors

Waiting for backordered items is one of the most common causes of remodeling delays. It's crucial to ensure that all key items are either on-site or arriving soon before starting demolition.

Phase 3: Demolition (2–4 Days)

Once permits are approved and materials are on hand, the demolition phase begins. This includes:

Removing old tiles, flooring, vanity, and fixtures

Disconnecting plumbing and electrical

Disposing of debris properly

For a small bathroom, demolition might take only a day or two, while larger or more complex spaces might need up to four days. Proper care must be taken to avoid damaging structural elements or plumbing that will be reused.

Phase 4: Rough-In Plumbing and Electrical (2–5 Days)

This phase includes modifying or updating the underlying infrastructure of the bathroom. Tasks include:

Installing or relocating water supply lines and drains

Running electrical wiring for outlets, lights, and fans

Adding blocking for wall-mounted vanities or grab bars

An inspection may be required at this stage, especially if plumbing or electrical is moved. Inspection scheduling can add 1–2 days depending on local codes.

Phase 5: Insulation and Drywall (2–4 Days)

With the plumbing and electrical rough-ins complete, insulation is added where needed. Then:

Drywall is installed, taped, and mudded

Several layers may be required with drying time in between

Sanding the walls smooth is essential for a clean paint finish

If moisture-resistant drywall is used (e.g., green board or cement board), this phase may also involve waterproofing areas such as the shower or bath alcove.

Phase 6: Painting and Surface Prep (1–2 Days)

Painting typically follows drywall installation. This is a relatively quick phase, but proper ventilation and drying time are crucial, especially if you're using mold-resistant or high-gloss bathroom paint.

Any surface preparation, such as sanding trim or priming, is also completed here.

Phase 7: Flooring Installation (1–3 Days)

Flooring choices greatly influence the timeline:

Vinyl or laminate: Quick and easy installation (1–2 days)

Ceramic or porcelain tile: Longer, requires mortar setting and grout curing (2–3 days)

Natural stone: May require sealing and more precise leveling

Professional installers often wait 24 hours between tile setting and grouting to allow adhesives to cure properly.

Phase 8: Cabinetry, Vanity, and Fixture Installation (2–4 Days)

This phase brings your bathroom to life:

Vanities, mirrors, medicine cabinets, and storage units are installed

Sinks, faucets, showerheads, and toilets are connected

Shower doors or glass enclosures are mounted

Lighting fixtures and electrical components are wired and tested

It’s a crucial stage where all finishing touches come together, and minor adjustments are made to align fixtures properly.

Phase 9: Final Touches and Inspection (1–2 Days)

The last phase includes:

Caulking and sealing joints

Installing trim and hardware (towel bars, toilet paper holders)

Final cleaning and debris removal

Final inspection, if required by the municipality

After passing inspection, your bathroom is officially ready for use.

Factors That Can Extend Your Bathroom Remodel Timeline

Even with careful planning, some factors may extend your remodeling timeline:

Special order materials with long shipping times

Unexpected plumbing or mold issues discovered during demolition

Change orders mid-project

Contractor availability

Permit delays or failed inspections

Working with an experienced contractor and finalizing every design element before beginning can significantly minimize risks and keep your project on schedule.

Bathroom Remodel Timeframe Based on Type

Remodel TypeEstimated Time
Cosmetic Refresh (paint, fixtures)1–2 weeks
Standard Remodel (new fixtures, tile, layout stays)3–6 weeks
Full Gut and Redesign (layout changes, plumbing/electric)6–10 weeks
Luxury Remodel (custom features, high-end materials)8–12 weeks or more

How to Speed Up Your Bathroom Remodel

Pre-order all materials before demolition

Hire a contractor with a solid schedule and references

Finalize the design and don’t change it mid-project

Secure permits early

Schedule inspections in advance

Time is money in remodeling efficient coordination between trades and early procurement makes a huge difference.

Conclusion

So, how long does a bathroom remodel take? The answer is: it depends but with proper planning, most standard bathroom renovations are completed within 3 to 6 weeks of active work. Including design and prep, allow for 6 to 10 weeks total.

A well-timed, well-executed bathroom renovation can add immense value to your home and daily life. Ensure that your expectations are aligned with your budget, contractor, and material availability to enjoy a stress-free remodeling experience.

Disclosure: Sanitarysupply.org receives an affiliate commission on some, but not all, of the products we recommend—but only if you decide to click through to the retailer's site and make a purchase.


You may also like

How To Finance A Bathroom Remodel
How To Start A Bathroom Remodel
Leave a Reply

Your email address will not be published. Required fields are marked

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}

Never miss a good story!

Subscribe to our weekly newsletter to keep up with the latest trends!